NTB

DVB-RCS Next Generation Support and Verification Testbed

STATUS | Completed
STATUS DATE | 01/08/2019
ACTIVITY CODE | 3A.040
NTB

Objectives

The original objective of this activity was to design and develop a software-only based Testbed implementing and fully validating key functions of the DVB-RCS2 standard.

The Testbed design and implementation should provide manufacturers and researchers with a validated reference design of DVB-RCS2 sub-systems implementing key RCS2 functions. The reference design focuses on the RCS2 terminal functions. The hub functionality is emulated as required for the validation of the terminal functions.

As an extension to the original contract, the testbed is upgraded to include also the physical layer, on the forward as well as the return link.

The reference design should be made available to RCS terminal manufacturers. The project should also provide feedback on the RCS2 standard and the RCS2 Guidelines documents to the TM-RCS group.

 

Challenges

The RSC2 standard and RCS2 Guidelines documents had not reached stable versions at the early phases of the project. Many questions came up at the detailed level that were not yet well covered in the documents.

Also, working in a distributed environment, with different operating systems, caused additional challenges (but finally resulted in a more flexible solution).

Plan

The main milestones in the project are:

Meeting, milestone

Schedule

Testbed Requirements Review

21.09.2011

Preliminary Design Review

08.12.2011

Critical Design Review

04.06.2012

 Testbed Acceptance Review

06.06.2013

Final review

02.07.2013

Final Presentation

17.09.2013

Phase2:

 

Baseline requirements Review

19.05.2015

Preliminary Design Review

18.06.2015

Critical Design Review

15.03.2016

Acceptance Test and Final Presentation

29.05.2016

Current Status

The project was started in June 2011. Final Review for phase 1 (software based only) was completed in July 2013.

Second phase, to include physical layer into the setup, was started in April 2015, and is planned completed in April 2016.